All tie ins are finished. Water is being turned back on. If you don’t have any water by 6:30 am, please call 580.748.2685 and we will get someone out to check.
All customers should anticipate a return to regular pressure by no later than mid-morning. Call the service line if you continue to have low pressure.
We truly appreciate the crews from Mach Resources who performed the majority of this work as ODOT’s contractor. We could not have done this without our great support from Myers Engineering. And of course, all of our Public Works crews, especially our Water crew, were vital to the completion of this water line relocation.
Thank you to the ladies who ensured these project updates went out, and thank you to everyone who took the time to help share the updates.
We planned for a four-hour routine tie in project, but finished with a complicated 12” line replacement under a US Highway. We have come to expect our projects won’t be routine - marrying our old infrastructure to the new. With a nice little rain storm added to the mix, we’re glad to have this wrapped up with no additional issues and no one getting hurt. All the professionals did a great job recognizing the problems and coming up with solutions as they encountered them.
As has been the case throughout this project, we have appreciated everyone’s patience and understanding.